CAE Air Canada Training Centre Expansion
HRCx provided commissioning services for an expansion of the Air Canada division of Pearson International Airport. The expansion includes a 3-storey new flight training centre that features an air simulator for new pilots and aircraft staff and a data centre complete with a chiller plant and boiler plant.
The commissioning scope of work includes the following:
• Development of the Commissioning Plan
• Review of complete mechanical, electrical and plumbing construction check lists
• Formal review of construction documents and submittals to complete performance test scripts
• Detailed review of manufacturer start-ups, pressure and leak test reports as well as final Test and Balance Report
• Conduct functional testing of new building systems
• Identify deficiencies and methods of issue resolution
• Complete retesting as required
• Review Building Operator training
• Prepare a Final Commissioning Report.
HAVC: Electric Steam Humidifiers, Domestic Hot Water Heaters, Baseboard Heaters, Cabinet Unit Heater, Computer Room A/C Units (CRAC and Condenser), Fan Coil Units (A/C and Condenser), Air Handling units, Single Duct Variable Volume Terminal units, Split System A/C Units
Building Automation System: Sequence of Operation (100% sampling rate), Temperature Control (100% sampling rate)
Plumbing and Fire Protection System: Sump Pump